Project Announcements – May 11, 2017
Swede Hill Water Main Project - Tentative Work Schedule
Weather Dependent

MAY 1, 2017:
Work started on 6TH STREET.  Crews are now directional boring lines down the east side of 6TH Street.   In a week or two, they will be working to tie the lines together so intersections in these areas may closed, detoured or flagged for one-lane traffic.


MAY 15, 2017:
Starting mid-week crews will begin work on 7TH STREET.  Please note, 7th Street will be a total reconstruct so the roadway will be torn up, unlike the directional drilling they are doing on 6th Street. 

Project #1 – Swede Hill Water Main Improvement Project 
This project includes the reconstruction of approximately 2,900 LF of aging and undersized water mains, approximately 450 LF of sanitary sewer, and approximately 150 LF of storm sewer.
 
Project Area Areas Include:
  • 4th Street – Between Rice and Sweeny Avenue
  • 5th Street – Between Manypenny and Rittenhouse Avenue
  • 6th Street – Between Old Military and Rittenhouse Avenue (Hwy. 13 will be detoured)
  • 7th Street -  Between Manypenny and Rittenhouse Avenue
  • Rittenhouse Avenue – Between 6th and 7th Street 
    ​This project will begin as soon as weather permits in Spring of 2017.  
Construction Requirements: 
  • Milestone #1 – By June 30, 2017 the Contractor shall have completed and placed in service the Hwy. 13 water main and services, binder course, and curb and gutter.   
  • Milestone #2 – The Contractor shall not start construction or store materials on Fourth Street until after June 13, 2017. 
  •  Contractor agrees the work will be substantially completed before July 30, 2017 and will be  fully complete by August 31, 2017. 
Please visit:  www.cityofbayfield.com (home page) to see a project map.
Special Note to property owners in these areas - Water Laterals
During Project #1, the City will be installing new water mains along portions of this project as well as replacing old services to the shut off.  This may be a good time for you to consider replacing any old-lines you have to new ¾” or 1” copper water services before they start to fail.  If you are interested, please contact a licensed plumber for a proposal.
Project #2 – City of Bayfield’s Waterfront Turning Point Park Project
PROJECT ON HOLD!   Consideration is being given to re-bid this project later this year.

Project Area:  Intersection of First Street and Wilson Avenue
The primary purpose of this project is to re-develop the Waterfront "Turning Point" element at First Street and Wilson Avenue into a new park area. T(Heavily impacted areas include the Apostle Islands Marina, and the East Dock Park. Both will remain open but traffic may be limited at times). 
 
 
Ongoing communication
The City of Bayfield realizes the significant disruption these projects will cause and we would like to keep you as up-to-date as possible.  Therefore, we will continue sending you e-newsletters and news blasts throughout the duration of these projects. 

 
THIS INFORMATION PREPARED BY:
Tom Kovachevich, PWD    AND   Billie Hoopman, Clerk
Any questions?  Please call 715-779-5712






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
City of Bayfield · 125 South First Street · P.O. Box 1170 · Bayfield, WI 54814 · USA

Email Marketing Powered by MailChimp